- 01
The challenge
-
Long set-ups and unplanned downtime.
-
Weak planning and performance control.
-
Scrap, movement and maintenance losses.
-
- 02
What we did
-
Reset planning and production control.
-
Reduced set-up, downtime and scrap.
-
Embedded visual management and coaching.
-
- 03
The results
$1.7msaved annually30%set-up reduction — with 25% less downtime3.6:1return on support investment
Spitfire helped us get clear on the issues holding us back and gave us a practical plan to improve. They worked side by side with the plant, keeping everyone focused on the changes with the biggest impact.
VP of Manufacturing — Kennametal